Deployment methodology for
Guralp Broadband Seismometer

- Sediment typical of continental margin
- Burial of sensor package is essential

3. Carry instrument to seafloor and place instrument into caisson


4. Connect logger to instrument to instrument and verify viability and orientation
- Requires ROV to connect to seismometer through logger




6. Allow to settle for two days
7. Connect ROV to logger and send commands to unlock gymbals and level sensors- Requires connecting ROV to instrument for 30 minutes to 1 hour
8. Cover sensor with a lexan top hat and canvas skirt to dampen bottom current noise
9. Return and check instrument Download data Re-level if necessary Connect second battery pack
10. Return and shutdown experiment
- Lock gymbals in sensor package
- Shutdown logger
- Disconnect battery pack
- Recover logger and sensor package with ROV