MOSS LANDING, California—MBARI has completed the construction of its new test tank and the
expansion of its existing Building B. The 10-meter-deep (35 feet) tank is
used for testing equipment, sensors, and underwater vehicles. The new
building also provides 24,000 square feet of office and lab space.
MBARI continues to be on the cutting edge of technology with this
construction project. Our structural and geotechnical engineers used
several new construction technologies to implement the architectural
design. Many of the products used to furnish the building were selected
because they are "green" or have minimal impact on natural
resources.
The original Building B, built in 1989, was constructed as a slab on
grade and designed to "float" on the surface in the occurrence
of an earthquake. The expansion, primarily because of the test tank being
eight meters below grade, needed to be firmly anchored in the subsurface
via soil-cement columns. These different design criteria dictated the
first step of construction, which was to improve the performance of the
existing building to match the new design. This requirement was met by a
process called injection grouting. Holes were bored through the building
foundation to a depth of 48 feet. Cementitious grout was then injected at
two-foot intervals at a pressure of 800 pounds per square inch to within
eight feet of the surface. The holes in the existing foundation were
capped with cement when the injection was completed. Two hundred fifty
eight injection sites were installed to stabilize the building.
Building of the expansion began with the demolition of an existing
structure on the site on February 14, 2000. The cleared site was improved
using a new technique that created subterranean soil-cement columns around
the test tank and in strategic building support locations. Using a special
augur-injection bit that drilled holes to a depth of 52 feet and
simultaneously injected cement slurry that mixed with the existing soil
(mostly sand). This process created concrete columns without first
excavating a hole and forming up a piling. Steel I-beams were inserted
into each supporting column point and in half of the columns around the
perimeter of the new test tank. The soil-cement columns around the test
tank also provided a cofferdam that halted salt water intrusion allowing
construction to proceed. The water table at MBARI is located only four
feet below grade. Additional injection grout points were installed to
provide support under the expansion site.
Following the installation of the soil-cement columns, the new test
tank was excavated. The walls of the test tank were poured in stages,
utilizing aluminum form structures and plywood. In an effort to conserve
resources, the forms were re-used for concrete pours throughout the
project. The test tank holds 375,000 gallons of water. The tank is 30 feet
wide, 45 feet across, and 35 feet deep, and is illuminated internally by
remote source fiber-optic light pipes. MBARI engineers and scientists have
already begun to use the tank to test equipment and underwater vehicles.
The Building B expansion also includes offices, laboratories and
staging areas providing the necessary space for MBARI to carry out its
mission.
.
###